Timeline

Oct 2013
Seller and I agreed on price of land  |  Signed building contract with Rivergum Homes  |  Engaged a conveyancer and signed contract for the land

Nov 2013
Bank loan approved  |  Paid deposit for the land  |  Land settlement!

Jan 2014
Exterior selections

Feb 2014
Interior selections part 1

Mar 2014
Interior selections part 2

Apr 2014
Plans submitted to council

Jun 2014
Council replied, not happy with development plans  |  Discussed with builder, decided to do a split-level to meet council requirements

Jul 2014
Engineers re-drafted plans, submitted to council

Aug 2014
Decided that I really wanted a raised ceiling in the back half of the house, so engineers got to re-draft plans  |  Got to raise the ceilings, and altering some window heights to suit new ceiling height

Sep 2014
Amended plans submitted to council!  |  Organise for boundary peg survey, retaining wall and removing vegetation from land  |  Finance application for construction

Oct 2014
DEVELOPMENT APPROVAL!

Nov 2014
1st physical structure gone up – Retaining wall part 1! | Construction finance approval

Dec 2014
Signed papers for bank loan | Start of site works

Jan 2015
Site works completed! | Retaining wall part 2

Feb 2015
Concrete slab down!

Mar 2015 
Timber frames and roof up!

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s